01 NCAC 30D .0305         DESIGNER/CONSULTANT SELECTION FOR OTHER THAN UNC SYS PROJECTS

Upon receipt of a letter from the Capital Projects Coordinator listing three firms in priority order along with recommendations and pre‑selection information, as requested by the SBC, the Secretary of SBC, upon determination that all information has been submitted, will place the request for consideration on the agenda for the next SBC meeting.

The Capital Projects Coordinator shall make a report to the SBC outlining the procedures that were followed and justification for the priority list of three firms. Upon a determination by the SBC that the standard procedures and criteria have been properly followed, the SBC will:

(1)           Select the firms in the priority order recommended by the state or agency; or

(2)           Select the firms in a different priority order from that recommended by the funded agency and give justification for such selection; or

(3)           Request a new priority list and give justification for such request.

 

History Note:        Authority G.S. 143‑315.25; 143‑135.26;

Eff. January 1, 1988;

Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. July 22, 2018.